Mitigation Controller: Adaptive Simulation Approach for Planning Control Measures in Large Construction Projects

  • Omar Kammouh(corresponding author)(Corresponding author)
    ,
  • Maria Nogal
    ,
  • Ruud Binnekamp
    ,
  • A.R.M. Wolfert
*Corresponding author for this work
  • Delft University of Technology
Output:
Contribution to journal
Article
Academic
Peer-review

Open access

Information

Output type

Output:
Contribution to journal
Article
Academic
Peer-review

Original language

English

Article number

04021093

Journal (Volume, Issue Number)

Journal of Construction Engineering and Management (Volume 147, Issue 8)

Publication milestones

  • Published - 01/08/2021

Publication status

Published - 01/08/2021

ISSN

0733-9364

Funding Details

This work is part of the research program D-to-MII (Design to Manage Interconnected Infrastructures) with Project No. 439.16.823, which is financed by the Dutch Research Council (NWO).
FunderFunding numbers
NWO
-

Abstract

Probabilistic Monte Carlo simulations are often used to determine a project's completion time given a required probability level. During project execution, schedule changes negatively affect the probability of meeting the project's completion time. A manual trial and error approach is then conducted to find a set of mitigation measures to again arrive at the required probability level. These are then implemented as scheduled activities. The mitigation controller (MitC) proposed in this paper automates the search for finding the most cost-effective set of mitigation measures using multiobjective linear optimization so that the probability of timely completion remains at the required level. It considers different types of uncertainties and risk events in the probabilistic simulation. Moreover, it removes the fundamental modeling error that exists in the traditional probabilistic approach by incorporating human control and adaptive behavior in the simulation. Its usefulness is demonstrated using an illustrative example derived from a recent Dutch construction project in which delay is not permitted. It is shown that the MitC is capable of identifying the most effective mitigation strategies allowing for substantial cost savings.

Bibliographical Note

Funding Information: This work is part of the research program D-to-MII (Design to Manage Interconnected Infrastructures) with Project No. 439.16.823, which is financed by the Dutch Research Council (NWO).

Metrics

Metrics

Scopus
citations
8
Download statistics
Download count
204
SciVal
FWCI
0.44
SciVal
Author count
4
SciVal
Paper percentile
49
SciVal
citations
8

PlumX, opens in new tab

Captures
52
Citation count
8