An alternative to safety stock policies for multi-level rolling schedule MRP problems

N.P. Dellaert, J. Jeunet

Onderzoeksoutput: Bijdrage aan tijdschriftTijdschriftartikelAcademicpeer review

10 Citaten (Scopus)
11 Downloads (Pure)

Samenvatting

We study the impact of positive lead times on the multi-level lot-sizing problem in a rolling schedule environment. We show how stockout situations may arise even in a context of deterministic demand. We therefore develop a procedure to avoid such stockouts and we compare its performance through a simulation study to a safety stock strategy. Simulation results show the superiority of the proposed procedure.
Originele taal-2Engels
Pagina's (van-tot)751-768
TijdschriftEuropean Journal of Operational Research
Volume163
Nummer van het tijdschrift3
DOI's
StatusGepubliceerd - 2005