Profit-maximization generation maintenance scheduling through bi-level programming

P. Mazidi, Y. Tohidi, A. Ramos, M.A. Sans-Bobi

Research output: Contribution to journalArticleAcademicpeer-review

18 Citations (Scopus)

Abstract

This paper addresses the generation maintenance scheduling (GMS) dilemma in a deregulated power system. At first, under a centralized cost minimization framework, a GMS is formulated and set as the benchmark (cost-minimization GMS). Then, the cost-minimization is changed into a profit-maximization problem of generation companies (GENCOs) and the GMS is developed as a bi-level optimization. Karush–Kuhn–Tucker conditions are applied to transform the bi-level into a single-level mixed-integer linear problem and subsequently, Nash equilibrium is obtained as the final solution for the GMS under a deregulated market (profit-maximization GMS). Moreover, to incorporate reliability and economic regulatory constraints, two rescheduling signals (incentive and penalty) are considered as coordination processes among GENCOs and independent system operators. These signals are based on energy-not-supplied and operation cost, and ensure that the result of profit-maximization GMS is in the given reliability and social cost limits, respectively. These limits are obtained from the cost-minimization GMS. Lastly, the model is evaluated on a test system. The results demonstrate applicability and challenges in GMS problems.
Original languageEnglish
Pages (from-to)1045-1057
Number of pages13
JournalEuropean Journal of Operational Research
Volume264
Issue number3
DOIs
Publication statusPublished - 1 Feb 2018

Keywords

  • Coordination process
  • Deregulated power system
  • Maintenance
  • OR in energy
  • Scheduling