Fourteen years of test experience with short-circuit withstand capability of large power transformers

R.P.P. Smeets, L.H. Paske, te

Research output: Chapter in Book/Report/Conference proceedingConference contributionAcademicpeer-review

4 Downloads (Pure)

Abstract

Experience is reported of short-circuit testing of large power transformers during the past 14 years by KEMA in the Netherlands. In total, 119 transformers > 25 MVA participated in the survey. KEMA shows that at initial access to standard IEC short-circuit tests, 28% failed initially in a wide range of power (119 transformers 25 - 440 MVA, 20 – 500 kV tested). No clear single cause for major failures could be identified; instead, a variety of defects was observed, mostly because of the dynamics associated with passage of short-circuit current. It is the author's observation that change in winding impedance due to short-circuit current passage is an excellent indicator for the short-circuit withstand capability. The authors comment on often heard considerations to replace short-circuit testing by design review procedures, mainly because of costs: ?? "There is no necessity to test because calculation methods are sufficiently adequate". ?? "There is no necessity to test because service experience with transformers is so good". ?? "The costs of testing have become prohibitively high and testing takes too much time". ?? "Short-circuit testing may have a deteriorating influence on the transformer under test". The authors conclude that design review, as the only component of quality assessment of power transformers, is not sufficient since 1/3 of the transformers that failed in service passed design review. No transformer failed in service had been short-circuit tested prior to installation. In addition, it is demonstrated that a major leap in quality improvement could be realised through full-power testing. It is concluded that although statistically every transformer faces several full short-circuits during its life, the current that really occurs at such a full shortcircuit current is smaller than the rated short-circuit for which the transformer is designed. In the future, however, this gap will narrow due to more efficient utilisation of the networks and growth of energy consumption. A brief overview is given on test methods and test installations of the author's laboratory.
Original languageEnglish
Title of host publicationProceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010
Place of PublicationMoscow, Russia
PublisherTravek
Publication statusPublished - 2010

Fingerprint

Power transformers
Short circuit currents
Testing
Networks (circuits)
Costs
Defects

Cite this

Smeets, R. P. P., & Paske, te, L. H. (2010). Fourteen years of test experience with short-circuit withstand capability of large power transformers. In Proceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010 Moscow, Russia: Travek.
Smeets, R.P.P. ; Paske, te, L.H. / Fourteen years of test experience with short-circuit withstand capability of large power transformers. Proceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010. Moscow, Russia : Travek, 2010.
@inproceedings{de2ee116a36e472fa742c6d700517154,
title = "Fourteen years of test experience with short-circuit withstand capability of large power transformers",
abstract = "Experience is reported of short-circuit testing of large power transformers during the past 14 years by KEMA in the Netherlands. In total, 119 transformers > 25 MVA participated in the survey. KEMA shows that at initial access to standard IEC short-circuit tests, 28{\%} failed initially in a wide range of power (119 transformers 25 - 440 MVA, 20 – 500 kV tested). No clear single cause for major failures could be identified; instead, a variety of defects was observed, mostly because of the dynamics associated with passage of short-circuit current. It is the author's observation that change in winding impedance due to short-circuit current passage is an excellent indicator for the short-circuit withstand capability. The authors comment on often heard considerations to replace short-circuit testing by design review procedures, mainly because of costs: ?? {"}There is no necessity to test because calculation methods are sufficiently adequate{"}. ?? {"}There is no necessity to test because service experience with transformers is so good{"}. ?? {"}The costs of testing have become prohibitively high and testing takes too much time{"}. ?? {"}Short-circuit testing may have a deteriorating influence on the transformer under test{"}. The authors conclude that design review, as the only component of quality assessment of power transformers, is not sufficient since 1/3 of the transformers that failed in service passed design review. No transformer failed in service had been short-circuit tested prior to installation. In addition, it is demonstrated that a major leap in quality improvement could be realised through full-power testing. It is concluded that although statistically every transformer faces several full short-circuits during its life, the current that really occurs at such a full shortcircuit current is smaller than the rated short-circuit for which the transformer is designed. In the future, however, this gap will narrow due to more efficient utilisation of the networks and growth of energy consumption. A brief overview is given on test methods and test installations of the author's laboratory.",
author = "R.P.P. Smeets and {Paske, te}, L.H.",
year = "2010",
language = "English",
booktitle = "Proceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010",
publisher = "Travek",

}

Smeets, RPP & Paske, te, LH 2010, Fourteen years of test experience with short-circuit withstand capability of large power transformers. in Proceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010. Travek, Moscow, Russia.

Fourteen years of test experience with short-circuit withstand capability of large power transformers. / Smeets, R.P.P.; Paske, te, L.H.

Proceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010. Moscow, Russia : Travek, 2010.

Research output: Chapter in Book/Report/Conference proceedingConference contributionAcademicpeer-review

TY - GEN

T1 - Fourteen years of test experience with short-circuit withstand capability of large power transformers

AU - Smeets, R.P.P.

AU - Paske, te, L.H.

PY - 2010

Y1 - 2010

N2 - Experience is reported of short-circuit testing of large power transformers during the past 14 years by KEMA in the Netherlands. In total, 119 transformers > 25 MVA participated in the survey. KEMA shows that at initial access to standard IEC short-circuit tests, 28% failed initially in a wide range of power (119 transformers 25 - 440 MVA, 20 – 500 kV tested). No clear single cause for major failures could be identified; instead, a variety of defects was observed, mostly because of the dynamics associated with passage of short-circuit current. It is the author's observation that change in winding impedance due to short-circuit current passage is an excellent indicator for the short-circuit withstand capability. The authors comment on often heard considerations to replace short-circuit testing by design review procedures, mainly because of costs: ?? "There is no necessity to test because calculation methods are sufficiently adequate". ?? "There is no necessity to test because service experience with transformers is so good". ?? "The costs of testing have become prohibitively high and testing takes too much time". ?? "Short-circuit testing may have a deteriorating influence on the transformer under test". The authors conclude that design review, as the only component of quality assessment of power transformers, is not sufficient since 1/3 of the transformers that failed in service passed design review. No transformer failed in service had been short-circuit tested prior to installation. In addition, it is demonstrated that a major leap in quality improvement could be realised through full-power testing. It is concluded that although statistically every transformer faces several full short-circuits during its life, the current that really occurs at such a full shortcircuit current is smaller than the rated short-circuit for which the transformer is designed. In the future, however, this gap will narrow due to more efficient utilisation of the networks and growth of energy consumption. A brief overview is given on test methods and test installations of the author's laboratory.

AB - Experience is reported of short-circuit testing of large power transformers during the past 14 years by KEMA in the Netherlands. In total, 119 transformers > 25 MVA participated in the survey. KEMA shows that at initial access to standard IEC short-circuit tests, 28% failed initially in a wide range of power (119 transformers 25 - 440 MVA, 20 – 500 kV tested). No clear single cause for major failures could be identified; instead, a variety of defects was observed, mostly because of the dynamics associated with passage of short-circuit current. It is the author's observation that change in winding impedance due to short-circuit current passage is an excellent indicator for the short-circuit withstand capability. The authors comment on often heard considerations to replace short-circuit testing by design review procedures, mainly because of costs: ?? "There is no necessity to test because calculation methods are sufficiently adequate". ?? "There is no necessity to test because service experience with transformers is so good". ?? "The costs of testing have become prohibitively high and testing takes too much time". ?? "Short-circuit testing may have a deteriorating influence on the transformer under test". The authors conclude that design review, as the only component of quality assessment of power transformers, is not sufficient since 1/3 of the transformers that failed in service passed design review. No transformer failed in service had been short-circuit tested prior to installation. In addition, it is demonstrated that a major leap in quality improvement could be realised through full-power testing. It is concluded that although statistically every transformer faces several full short-circuits during its life, the current that really occurs at such a full shortcircuit current is smaller than the rated short-circuit for which the transformer is designed. In the future, however, this gap will narrow due to more efficient utilisation of the networks and growth of energy consumption. A brief overview is given on test methods and test installations of the author's laboratory.

M3 - Conference contribution

BT - Proceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010

PB - Travek

CY - Moscow, Russia

ER -

Smeets RPP, Paske, te LH. Fourteen years of test experience with short-circuit withstand capability of large power transformers. In Proceedings of the Travek VIIth int. science and technical conference on large power transformers and diagnostic systems, Travek, Moscow, 22-23-06-2010. Moscow, Russia: Travek. 2010